The October 2024 US East and Gulf Coast port strike
The ILA strike shut US East and Gulf Coast ports for three days in October 2024. What it did to queues, surcharges and transatlantic rates.
Three days that closed half of US container imports
On 1 October 2024 the International Longshoremen's Association (ILA) walked out at ports from Maine to Texas after its master contract with the United States Maritime Alliance (USMX) expired. Around 45,000 dockworkers stopped work at 36 ports that handle about half of the cargo moving in and out of the United States by ship. It was the ILA's first major stoppage since 1977. The dispute was about wages and, above all, automation at terminals.
The scale mattered. An HSBC research note quoted by Seatrade Maritime said East and Gulf Coast ports had handled 55.5% of US container imports in 2024 up to September. For cargo from Europe, the Mediterranean and Latin America there was no realistic alternative: Canadian and Mexican east coast ports could not absorb that volume.
A wage deal and a 15 January deadline
On the evening of 3 October the ILA and USMX announced a tentative agreement on wages and extended the master contract until 15 January 2025, so that talks on the remaining issues could continue. Work resumed on 4 October. Reports by the BBC and Reuters put the wage increase at about 62% over six years; the union had asked for 77% and USMX had offered close to 50%. Automation was left for the next round, which meant the market spent the rest of the quarter with a second strike risk on the calendar.
That risk did not materialise. On 8 January 2025 the two sides announced a tentative six-year master contract that allowed semi-automation with job guarantees, removing the threat of a new walkout on 16 January.
Queues, surcharges and the freight bill
Even three days left a visible backlog. Xeneta counted 44 ships queuing outside the affected ports early on 4 October and more than 120 more en route. Hapag-Lloyd told Reuters that clearing the backlog could take three to four weeks; before the strike Maersk had estimated four to six weeks of recovery for every week of closure.
Rates moved before a single box was delayed. Xeneta data showed average spot rates from North Europe to the US East Coast at USD 2,900 per FEU on 4 October, up 58% since the end of August, while North Europe to the US West Coast rose 48% to USD 4,450 per FEU as cargo looked for other gateways. In September carriers had also announced strike surcharges: CMA CGM USD 1,500 per TEU on imports into East and Gulf Coast ports from 11 October, and Hapag-Lloyd a USD 1,000 per TEU Work Disruption Surcharge from 18 October. After the deal Hapag-Lloyd withdrew its WDS and extended detention free time to 6 October, but residual delays at ports, rail and trucking lasted for weeks.
Why a US strike reaches other trade lanes
Ships stuck off New York or Savannah return late to Asia and Europe. Xeneta warned that the knock-on effect would hit schedules in the run-up to the Lunar New Year at the end of January 2025, at a time when Asia trades were already tight because of Red Sea diversions. For buyers of building materials shipped in containers, such as tiles, fittings, insulation or cable, that means blank sailings, rolled bookings and less equipment at origin, even on routes that never touch the US.
What this means for an importer
- Know the labour calendar. Master contract expiry dates at major gateways are public; treat the months before them as a risk window for booking and pricing.
- Read the surcharge clause. On CFR or CIF terms, ask the seller whether announced emergency surcharges are included in the price or will be passed on; get it in writing.
- Watch free time. During port closures demurrage and detention can run while nothing moves. Ask the forwarder which carrier or terminal waivers apply.
- Add buffer to delivery dates. A short strike can still mean three to six weeks of disruption, so leave room in the L/C latest shipment and expiry dates.
- Check knock-on effects. Delayed US loops pull ships and boxes away from other trades; confirm equipment availability at the loading port early.
Sources
- www.xeneta.com/news/agreement-reached-to-end-us-port-strike-but-supply-chains-will-take...
- www.aljazeera.com/news/2024/10/4/us-dockworkers-union-to-suspend-strike-after-reaching-...
- www.seatrade-maritime.com/containers/container-lines-roll-out-us-east-coast-surcharges-...
- www.hapag-lloyd.com/en/services-information/offices-localinfo/local-news/2024/10/strike...
- www.cnn.com/2025/01/08/business/us-dockworkers-port-employers-agreement