Transformer shortage 2023: lead times stretch to years

Distribution and power transformer lead times stretched to years in 2023 as electrical steel and copper costs rose. How contractors should plan buying.

From months to years

By 2023 transformers had become one of the tightest items in power and building projects. In a June 2023 analysis, the US Congressional Research Service (CRS) quoted the National Rural Electric Cooperative Association: distribution transformer orders that used to be filled in two to four months were taking 22 to 33 months. At an April 2023 Senate hearing, a senator asked the Energy Secretary whether users should expect lead times of up to two to four years and more. A report from the National Renewable Energy Laboratory (NREL), published in early 2024, described lead times of up to two years for distribution transformers, a fourfold increase on pre-2022 levels, and price increases of as much as four to nine times over three years.

Large units wait longest

For large power and generator step-up transformers the queue was longer still. Wood Mackenzie reported that average transformer lead times rose from around 50 weeks in 2021 to about 120 weeks by 2024, with large units ranging from 80 to 210 weeks. Transformer prices rose 60 to 80 percent on average from January 2020, and only around 20 percent of US transformer demand could be met by domestic supply. Most published data come from the United States, where the shortage was best documented, but the same materials and many of the same manufacturers serve other markets.

The materials behind the queue

The core of most transformers is grain-oriented electrical steel (GOES), and that is where supply is thinnest. Wood Mackenzie said GOES prices roughly doubled from January 2020 and peaked in the fourth quarter of 2023, while copper rose about 50 percent over the same period. According to the Department of Energy analysis cited by CRS, Cleveland-Cliffs is the only US maker of GOES, with other sources in the European Union, China and Russia. DOE's May 2023 critical materials assessment listed electrical steel as a near-critical material. A January 2023 DOE proposal to raise distribution transformer efficiency standards, which could have pushed more cores towards amorphous steel, drew a June 2023 letter from 47 senators urging the department not to worsen the shortage.

Why demand kept rising

Demand came from several directions at once: replacement of ageing equipment, storm recovery, new renewable generation and grid connections, and electrification of heating and transport. NREL estimated that the distribution transformer capacity needed by 2050 could be 160 to 260 percent above 2021 levels. Wood Mackenzie noted that manufacturers who cut output during the pandemic struggled to ramp back up, and skilled labour remained a bottleneck.

A procurement plan for contractors

  • Order transformers first. On many projects the transformer, not the building, now sets the energisation date. Place the order as soon as the single-line diagram and ratings are frozen.
  • Freeze the specification early. Changing voltage, vector group, loss values or cooling after the order can send a unit back to the end of the queue.
  • Get the production slot and the core steel source in writing, and check whether the delivery date depends on them.
  • Escalation clauses linked to copper and electrical steel are common in a tight market. Agree the index and a cap instead of accepting an open formula.
  • Widen the field: consider standard ratings and other qualified manufacturers, including in other regions, but check type test reports and the utility's approved list.
  • Plan the logistics with the order. Large power transformers move as heavy breakbulk cargo, so port handling, route surveys and site access take time to arrange.

The lesson from 2023

In 2023 transformers moved from a catalogue item to a long-lead strategic purchase. The cost of waiting is not only a higher price; it can mean months in which an otherwise finished project stands without power.

Sources

  1. www.congress.gov/crs_external_products/IN/PDF/IN12179/IN12179.2.pdf
  2. www.woodmac.com/news/opinion/supply-shortages-and-an-inflexible-market-give-rise-to-hig...
  3. docs.nlr.gov/docs/fy24osti/87653.pdf