Force majeure in 2020: CCPIT certificates and the new ICC clauses

Chinese exporters collected thousands of CCPIT force majeure certificates in early 2020, and the ICC updated its clauses in March. What it means.

Certificates by the thousand

As factories in China stayed closed after the Lunar New Year, exporters turned to a tool that most foreign buyers had rarely seen: the force majeure certificate issued by the China Council for the Promotion of International Trade (CCPIT). The first one went on 2 February to a manufacturer in Zhejiang province. According to Xinhua, it was used to excuse a 2.4 million yuan overseas order that could otherwise have triggered 30 million yuan in compensation. By 14 February CCPIT had issued 1,615 certificates to companies in more than 30 sectors, covering contracts worth 109.9 billion yuan, about USD 15.7 billion. By 27 February the count had reached 4,318, issued through 99 trade promotion agencies and chambers, covering contracts worth 330.8 billion yuan, or USD 47.2 billion. CCPIT said application rates were notably high in manufacturing, wholesale and retail, construction, and power generation equipment.

What a certificate does and does not do

A CCPIT certificate records facts: that quarantine, road closures and government orders affected a company in a given place and period. It is useful evidence. It is not a court ruling. Whether a seller is excused depends on the force majeure clause in the contract and on the governing law, and press coverage at the time, including the South China Morning Post, questioned how far the certificates would protect Chinese companies abroad. Under English law, for example, a typical clause relies on a closed list of events, so an event outside the list may give no relief under the clause at all. A buyer who receives a certificate should read it against the contract, not instead of it.

The ICC updates its model clauses

In March 2020 the International Chamber of Commerce published revised Force Majeure and Hardship Clauses, replacing the 2003 versions. The main points:

  • There is now a long form and a short form; the short form is aimed at smaller companies but gives less detail.
  • Force majeure requires proof that the impediment was beyond the party's reasonable control, could not reasonably have been foreseen when the contract was made, and its effects could not reasonably have been avoided or overcome.
  • Listed presumed events include plague and epidemic, and acts of authority or compliance with a government order. For these the affected party only has to prove the third condition.
  • Failure of a subcontractor or supplier counts only if the conditions are met for that third party too.
  • Notice must be given without delay; relief starts from the impediment if notice is prompt, otherwise from when notice arrives.
  • Either party may terminate if the impediment lasts more than 120 days, replacing the old reasonable period test.

The revised hardship clause also changed. Where the parties cannot agree new terms after an event makes performance excessively onerous, the contract now chooses between three options: termination by the party invoking hardship, adaptation or termination by a judge or arbitrator, or a declaration of termination by a judge or arbitrator.

Lessons for buyers of building materials

  • Check whether your purchase contract has a force majeure clause at all, and whether it lists epidemics and government orders.
  • Ask for written notice with dates and the specific orders affected, not a general letter.
  • Agree in advance what happens to advance payments if the contract ends under force majeure.
  • Consider incorporating the ICC clause by reference, with a fixed termination period such as 120 days, so a long stoppage does not leave both sides locked in.
  • Remember that your own obligations to the site or end buyer may not be excused by your supplier's certificate.

Sources

  1. www.xinhuanet.com/english/2020-02/17/c_138791495.htm
  2. english.ccpitbj.org/web/static/articles/catalog_2c94bbf02fd8b281012fd8debea40005/articl...
  3. www.scmp.com/economy/china-economy/article/3052277/coronavirus-doubts-raised-over-wheth...
  4. iccwbo.org/wp-content/uploads/sites/3/2020/03/icc-forcemajeure-hardship-clauses-march2020.pdf
  5. dlapiper.com/en/insights/publications/2020/04/icc-updates-its-force-majeure-and-hardshi...